An Olympic size pond in the central town of Seremban, a city south of Kuala Lumpur catches the attention of many people entering town. Most of Seremban folk are aware that the pond is actually an abandoned shopping complex project. It is among one of the projects abandoned during the economic downturn in the late 1990s.

However, 15 years later, the state government announces to revive the abandoned Olympic size pond’s project as part of the Greater Kuala Lumpur/Klang valley National Key Economic Area Initiative. This real case study illustrates several issues surrounding an abandoned commercial project that is of public interest. Many of these issues remained unresolved until today.

Please request the Journal from us via the button below.

Q

Request Form

You might also be interested in

Verified by MonsterInsights